How do you estimate a 100A to 200A panel upgrade?

How to scope and price a 100 amp to 200 amp service upgrade: load check, permit, utility coordination, inspection steps and a worked estimate with the math.

THE SHORT ANSWER

Confirm the home needs 200 amps with a load calculation, then price the full service: meter socket, service conductors, panel, grounding and bonding, permit, utility coordination and inspection. Price from direct cost and your target margin. Permit rules, utility steps and code edition vary by jurisdiction.

  • A service upgrade is a permitted, inspected job in nearly every jurisdiction, and the rules depend on the local authority and the adopted code edition.
  • The load calculation, not the home's age, proves the new size. NEC 220.82 is the optional dwelling method.
  • Scope includes more than the panel: meter socket, service conductors, grounding electrode system and bonding.
  • Utility disconnect, reconnect and any meter work are scheduled separately from your crew.
Updated October 27, 2026 · By the Sunwell team

How do you decide whether a home needs 200 amps?

Run a load calculation for the home as it will be used, including new loads such as an electric vehicle charger, heat pump or induction range. The optional method in NEC 220.82 turns the connected loads into a demand in amps, as the load calculation guide shows. If the answer is near or over 100 amps, a bigger service makes sense.

Also check the condition of the existing equipment: a damaged meter base, a panel with known problems, or no room for needed circuits can justify the upgrade on their own.

What is in the scope of a service upgrade?

Write the scope as a list so the customer and the inspector see the same job. Typical items are the meter socket, service entrance conductors or overhead mast, the new main panel, the main breaker, branch circuit breakers and reconnection of existing circuits, the grounding electrode system and bonding, and patching.

Conductor size is set by the service rating and the code table your jurisdiction adopts, so confirm sizes against the adopted edition rather than a rule of thumb.

What are the permit, utility and inspection steps?

The order below is common, but your utility and authority having jurisdiction decide the details. Ask both before you quote the schedule.

Typical sequence: pull the permit with the load calculation if required, schedule the utility disconnect, replace the equipment, pass the inspection, then have the utility reconnect and set the meter. Some utilities will not reconnect until inspection passes.

What does a worked estimate look like?

1418 Ridge Rd, 100A to 200A overhead service. These are example costs, so replace them with your own.

Materials: 200A panel $380, meter socket $210, service conductors and mast hardware $520, grounding and bonding parts $140, breakers and fittings $350. Total $1,600.

Labor: 12 hours x $95 loaded cost = $1,140. Permit: $180. Direct cost: $1,600 + $1,140 + $180 = $2,920.

Price at a 35 percent margin: $2,920 / 0.65 = $4,492.31, rounded to $4,492. Gross profit is $4,492 - $2,920 = $1,572, which is 35.0 percent of the price.

Add separate lines for items that vary: trenching or an underground service, relocating the meter, utility fees, drywall or stucco patching, and any code corrections the inspector requires.

How do you write the proposal to avoid disputes?

State who pulls the permit, who schedules the utility, and that the outage window depends on the utility. Say what is not included, such as correcting existing wiring defects found behind the old panel. Offer the customer a priced option for added circuits or a subpanel, since the walls are already open.

Step by step

  1. Run the load calculation. Use the NEC 220.82 optional method for the home and any planned loads, and keep the worksheet with the job.
  2. Check the site. Inspect the meter base, mast, service conductors, grounding and panel location, and note any trenching or relocation.
  3. Confirm permit and utility steps. Ask the local building department and the utility about forms, fees, disconnect scheduling and inspection requirements.
  4. Build the price. Total materials, labor and permit, divide by (1 - target margin), and add lines for variable items.
  5. Close out. Pass inspection, confirm the utility reconnect and meter set, and leave the customer a labeled panel directory.
Run the numbers yourselfOpen the free calculator

Running a electrical company? See how Sunwell handles electrical jobs from first call to paid.

Sources: EC&M: Dwelling Load Calculations Per the National Electrical Code

Questions

What shops ask before they switch.

Does a panel upgrade need a permit?

In nearly every jurisdiction, yes, with an inspection. The building department and utility set the exact process, so confirm locally.

Why upgrade from 100 amps to 200 amps?

Typical reasons are a load calculation near or above 100 amps, new loads such as EV charging or a heat pump, or damaged or crowded equipment.

Who disconnects and reconnects the power?

Usually the utility. Schedule it with them, and note in the proposal that your timeline depends on their availability.

How should I price a panel upgrade?

Total your material, labor and permit costs and divide by one minus your target margin. Add separate lines for trenching, meter relocation and patching.

You shouldn't pay for software you don't use. So every team gets a quote built for it.

CUSTOM QUOTE

Get a custom quote.

Tell us your team size, locations and what you use today. We send a written quote within one business day and can walk you through Sunwell on your own data.

STEP 1 OF 3 · YOUR BUSINESS

Your business

Reply within one business dayNo contract to startData move includedCustomer portal always free

Required. We only use these details to contact you about Sunwell. We never sell them.

What happens next

  1. 1A written quote in one business day

    Sized to your team, locations and what you turn on.

  2. 2A walkthrough on your own data

    See your jobs and pricebook on the board, not a demo account.

  3. 3We move you over

    Customers, jobs and pricebook imported, office and crews trained. Guided setup always included.

Not ready to talk yet?

Get one short update a month on what is new in Sunwell. No spam.

Book a demo

30 minutes on your own workflow

Pick a time

Online booking is paused right now. Email sean@sunwellcrm.com and we'll set a time.

Loading open times
OpenAlmost fullUnavailable
Next available
Morning
Afternoon

Your details

We email you a 6-digit code to hold the time. Nothing is booked until you enter it.

Check your email

We sent a 6-digit code to . Enter it to lock in . We hold the time for 10 minutes.

You're booked.

30-minute demo · private video link

Open your video link

A calendar invite with the video link is in your email. To move it, reply to that email.

Before you go

Want a quote without a call?

Leave your email. We send a few quick questions about your team, then a written quote. No spam.